City staff have made their recommendations for road repairs for 2020 and 2021, and the recommendation is.... city wide!
The city and their engineering consultant have identified spots city wide in need of concrete patching. Some existing concrete pavement and curbs would be removed and replaced. In a few spots, drainage structures and some driveways may also need some work.
By making it a two year contract, the city might be able to achieve some costs savings through economies of scale and locking in prices for two years.
If approved by city council, work would like begin in May 2020 and, weather permitting, go into December 2020 for the first year's work.
Click the image below to see a more detailed version of the map.